NEW QUESTION 1

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

  • A. Least cost
  • B. Qualifications only
  • C. Sole source
  • D. Fixed budget

Answer: B

NEW QUESTION 2

Which Manage Communications tool or technique focuses on identifying and managing barriers?

  • A. Communication methods
  • B. Information technology
  • C. Communication models
  • D. Information management systems

Answer: C

NEW QUESTION 3

Which of the following Project Communication Management processes uses performance reports as an input?

  • A. Manage Stakeholder Expectations
  • B. Report Performance
  • C. Distribute Information
  • D. Plan Communications

Answer: C

NEW QUESTION 4

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

  • A. There is a cost underrun.
  • B. There is a cost overrun.
  • C. The project may not meet the deadline.
  • D. The project is 20 days behind schedule.

Answer: B

NEW QUESTION 5

A graphic display of project team members and their reporting relationships is known as a:

  • A. Resource calendar.
  • B. Project organization chart.
  • C. Resource breakdown structure (RBS).
  • D. Responsibility assignment matrix (RAM).

Answer: B

NEW QUESTION 6

Which contract type is least desirable to a vendor?

  • A. Fixed price with economic price adjustment (FPEPA)
  • B. Firm fixed price (FFP)
  • C. Cost plus fixed fee (CPFF>
  • D. Cost plus award fee (CPAF>

Answer: B

NEW QUESTION 7

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

  • A. Cost-reimbursable contracts
  • B. Time and Material contracts (T&M)
  • C. Fixed-price contracts
  • D. Cost Plus Fixed Fee Contracts (CPFF)

Answer: C

NEW QUESTION 8

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

  • A. Program Management Body of Knowledge Guide
  • B. The Standard for Program Management
  • C. Organizational Project Management Maturity Model (OPM3$)
  • D. Guide to the Project Management Body of Knowledge (PMBOKĀ®)

Answer: D

NEW QUESTION 9

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

  • A. Acquisition
  • B. Negotiation
  • C. Virtual team
  • D. Pre-assignment

Answer: D

NEW QUESTION 10

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?

  • A. Manage Quality
  • B. Plan Quality Management
  • C. Control Quality
  • D. Plan Scope Management

Answer: B

NEW QUESTION 11

Which of the following is a narrative description of products, services, or results to be delivered by a project?

  • A. Project statement of work
  • B. Business case
  • C. Accepted deliverable
  • D. Work performance information

Answer: A

NEW QUESTION 12

Change request status updates are an output of which process?

  • A. Perform Integrated Change Control
  • B. Direct and Manage Project Execution
  • C. Close Project or Phase
  • D. Monitor and Control Project Work

Answer: A

NEW QUESTION 13

Change requests are an output from which Project Integration Management process?

  • A. Direct and Manage Project Execution
  • B. Develop Project Management Plan
  • C. Close Project
  • D. Develop Project Charter

Answer: A

NEW QUESTION 14

What are the objectives of Initiation processes?

  • A. Initiation processes are performed in order to develop the project charier and Identify stakeholders.
  • B. Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
  • C. Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
  • D. Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Answer: D

NEW QUESTION 15

What tool should a project manager use to efficiently manage project resources?

  • A. List of project resources
  • B. Resource breakdown structure
  • C. Resources detailed in the project scope
  • D. Resource requirements

Answer: C

NEW QUESTION 16

When should quality planning be performed?

  • A. While developing the project charter
  • B. In parallel with the other planning processes
  • C. As part of a detailed risk analysis
  • D. As a separate step from the other planning processes

Answer: B

NEW QUESTION 17

Which of the following strategic considerations often results in project authorization?

  • A. Customer requests and/or issue resolution
  • B. Stakeholder expectations and/or strategic opportunity (business need)
  • C. Technological advancement and/or senior executive request
  • D. Market demand and/or legal requirements

Answer: D

NEW QUESTION 18

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

  • A. enterprise environmental factors.
  • B. organizational process assets.
  • C. project management plan,
  • D. project funding requirements.

Answer: A