We provide real PMI-ACP exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI PMI-ACP Exam quickly & easily. The PMI-ACP PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI PMI-ACP dumps pdf and vce product and material, you can easily pass the PMI-ACP exam.

Also have PMI-ACP free dumps questions for you:

NEW QUESTION 1
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager What should the Scrum Master do?

  • A. Dismiss the learn member
  • B. Discuss the situation with the functional manager
  • C. Report the functional manager to the project sponsor
  • D. Demand that the functional manager respect the protect charter

Answer: B

NEW QUESTION 2
A product owner asks a newly formed scrum team how many story points will be completed m a sprint What should the scrum master do?

  • A. Engage the team to determine the sprint velocity based on previous agile projects
  • B. Average the sprint velocity based on input from ream members
  • C. Share the sprint velocity obtained from the sponsor with the team
  • D. Run multiple sprints before determining the sprint velocity with the team.

Answer: A

NEW QUESTION 3
During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good.
What should the agile team lead do?

  • A. Require the team to try only those ideas that will ensure success.
  • B. Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.
  • C. Associate idea successes and failures with the team's incentive plan to ensure accountability.
  • D. Encourage the team to try the ideas, even if failure may be the outcome.

Answer: D

NEW QUESTION 4
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?

  • A. Work with the agile team and product owner to agree on the definition of done.
  • B. Ask the project sponsor to determine whether the product is completed.
  • C. Plan another review after the product has been tested.
  • D. Add testing to the backlog, and have the product owner reprioritize.

Answer: A

NEW QUESTION 5
An agile practitioner wants to communicate the effect of technical debt on the project What should the practitioner do?

  • A. Post and discuss rises in the burn down chart
  • B. Adjust story points to account for technical debt.
  • C. Log technical debt as an impediment.
  • D. Add refactoring tasks to all stones

Answer: C

NEW QUESTION 6
During a review session an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value
What should the team have done to prevent this?

  • A. Reprioritized requirements prior to committing to iteration work
  • B. Ensured that requirements remained stable during the iteration cycle
  • C. Had stakeholders focus on items created after the product backlog was initially built
  • D. Worked on features rather than a set of components

Answer: D

NEW QUESTION 7
The amount of information captured in the project's defects is varying within the development team. Team members are becoming frustrated with the defect quality inconsistencies and the frequent clarification required.
What should be done to address the issue?

  • A. Stop the current iteration to discuss defect quality issues and explore solutions.
  • B. Discuss and explore solutions in the next planning meeting and take corrective actions as required.
  • C. Generate insights at the next retrospective and adjust processes as decided by the team.
  • D. Assign corrective actions to the backlog for the team to identify the mandatory defect information.

Answer: C

NEW QUESTION 8
During iteration planning, it was determined that an epic should be decomposed. What was the determining factor?

  • A. Size and priority
  • B. Minimum marketable features
  • C. Release plan
  • D. Sprint mapping

Answer: A

NEW QUESTION 9
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?

  • A. Team B has underestimated scope compared to team A.
  • B. Team A is more confident in delivering velocity than team B.
  • C. Both teams need to indicate their proposed technology before the estimates can be analyzed.
  • D. Both teams have estimated the project to be of same size.

Answer: D

NEW QUESTION 10
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?

  • A. Schedule regular meetings with the scrum team to write, groom, and size user stories.
  • B. Focus on stories based on the highest number of story points to first address those items with the highest value.
  • C. Seek regular input from project stakeholders, and reflect this input in the backlog's priorities.
  • D. Schedule in-person, monthly meetings with key stakeholders to review the project's progress.

Answer: C

NEW QUESTION 11
During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal.
What practice is the agile facilitator implementing?

  • A. Building openness and transparency on the project's health and status
  • B. Facilitating conflict resolution among executive team members
  • C. Using active stakeholder involvement to build features in an incremental and iterative approach
  • D. Seeking continuous feedback from executive team members

Answer: A

NEW QUESTION 12
During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

  • A. Positively acknowledge the list and share it with management
  • B. Immediately have the team implement the initiatives
  • C. Help the team choose one or two initiatives for immediate implementation.
  • D. Ask the team to choose and implement the most complex initiative

Answer: C

NEW QUESTION 13
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because
both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?

  • A. Provide both project teams with the highest priority needs.
  • B. Request the project teams' questions in writing prior to the next meeting.
  • C. Facilitate a meeting with each team and the product owner to find a solution.
  • D. Provide both teams with each project's documentation.

Answer: C

NEW QUESTION 14
During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

  • A. Notify the product owner and begin resolution.
  • B. Communicate the issue to the team in the next stand up meeting.
  • C. Immediately begin resolution, and communicate it to the team during the retrospective.
  • D. Work on the next activity, and communicate it to the team during the retrospective.

Answer: C

NEW QUESTION 15
A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

  • A. Shared vision statement and sprint goal
  • B. Release burnup chart
  • C. Velocity metrics
  • D. Iteration burndown chart

Answer: C

NEW QUESTION 16
Outing a review session a customer representative is concerned that a story fails to satisfy the scope of work. However the product owner declares that the scope of work is complete What should be done with this story?

  • A. Mark it as incomplete and prioritize it for the next sprint
  • B. Mark it as complete, since the product owner has the final say
  • C. Discard it and create a new story for the remaining scope of work
  • D. Mark it as complete, since the team completed the scope of work

Answer: D